Pedigo Expansion
Completed by Perlo’s SPG team, this project included demolishing a portion of the space to prepare for the two-story build-out.
  • Location: Vancouver, Washington
  • Architect: VLMK Engineering + Design
  • Owner: Pedigo

Features include a conference room, training room, and showroom for potential clients. Special attention was required to navigate complex plumbing challenges to install four (4) new RTUs, avoid obstacles with the existing underground plumbing, and add new transformers for increased power capacity. Additionally our team completed upgrades for European circuit requirements at six (6) locations in Pedigo’s testing room to ensure their products can hold up to the European UL standards. All work was completed within an occupied facility that operates 22 hours a day, six days a week, with measures employed to contain the work area and protect sensitive equipment, such as the tank farm.